Foreigners
Off-Plan Property Disputes in Morocco: Developer Delays, Refunds and Buyer Protection

Quick answer
An off-plan (VEFA) dispute in Morocco is governed by the current framework in articles 618-1 to 618-20 of the Code of Obligations and Contracts, as reformed by Law 107-12. The preliminary contract can only be signed after the building permit, and the law caps what you can be asked to pay at each construction stage. A developer is not automatically late the day after the deadline: it may have a lawful additional period of up to six months if it told you one month before. A delay penalty of 1% per month (capped at 10% per year) can apply to whichever party defaults, but only one month after a formal notice. The developer must provide a completion or refund guarantee, and once you have paid more than half the price you may register a prénotation on the title. Termination compensation is set by law at 15% or 20% of amounts paid depending on the stage, and paying instalments does not make you the owner until the final deed and registration.
A practical guide for a buyer who has already paid for an off-plan (VEFA) property in Morocco and now faces a developer problem: how to place yourself in the legal sequence and what remedies actually exist.
What is your actual problem?
You signed for an apartment that was still being built. You have already paid several instalments. The delivery date is approaching — or has passed — and now the developer says the works are continuing, asks for another payment, or has handed over something that no longer matches what was promised. This guide is for that moment.
An off-plan dispute is not a single problem with a single answer. Before anything else, name what is actually happening: is it a delay, a project that has stopped, payments demanded ahead of the construction, a missing guarantee, changed plans, a property that does not conform, a final sale that is not happening, or a wish to pull out and recover your money?
The right response depends on where you are in the legal sequence of a VEFA transaction, what you signed, how much you have paid against the construction actually done, and whether the developer is genuinely late. The sections below walk through that sequence so you can locate your own situation inside it.
What off-plan (VEFA) means — and what it does not
Off-plan purchase in Morocco — vente en l'état futur d'achèvement (VEFA) — is governed by articles 618-1 to 618-20 of the Code of Obligations and Contracts, as reformed by Law 107-12. Under article 618-1 it is a sale in which the developer undertakes to build a property within a set period and to transfer ownership to the buyer, the price being paid progressively as the works advance.
The essential point is that this is not the same as buying a finished apartment. You are paying, over time, for something that does not yet exist, which is exactly why the law surrounds the transaction with protective rules on the contract form, the payment timing, guarantees and delivery. Knowing those rules is what turns a worried buyer into one who can act.
The reservation contract
Many purchases begin with a reservation contract. Under the current framework (articles 618-3 ter and 618-3 quater) a reservation contract cannot even be concluded before the developer has obtained the building permit. Its validity is limited to a maximum of six months and it is non-renewable; it must lead either to a preliminary sale contract or to withdrawal and a refund.
The buyer has a right to withdraw within one month of the reservation contract, and on withdrawal the developer must return the whole advance within seven days. The sums paid at reservation are placed in a special bank account and are protected from disposal or seizure during the withdrawal period. If someone tells you a reservation locks you in indefinitely, that is wrong — but note that this one-month withdrawal right belongs to the reservation stage, not to the later stages of the deal.
The preliminary contract and the building permit
The core document is the preliminary sale contract. Under article 618-5 it may only be concluded after the developer has obtained the building permit — so the building permit, not the state of the foundations, is the legal gateway to this contract. Verifying that the permit exists before you commit is one of the most useful checks you can make.
As to form, article 618-3 requires the preliminary contract to be drawn up, on pain of nullity, either by an authentic (notarial) act or by an act drawn up by a professional legally authorized to do so. A preliminary contract that ignores this form is exposed to nullity, which is why the document should never be a simple private paper signed in a sales office without the required formality.
The legal payment stages
- At most 5% of the price at the reservation contract.
- At most a further 5% at the preliminary contract where a reservation contract existed — or up to 10% at the preliminary contract where there was no reservation.
- At most 10% at the commencement of the works.
- At most 60% in total, spread across three construction stages agreed by the parties: (a) foundations to ground-floor level; (b) completion of the structural (gros-œuvre) works; (c) finishing works plus the habitation permit or conformity certificate.
- At most 20% at the final sale contract and handover of the keys.
- A payment demanded before the reservation or preliminary contract has no legal effect under article 618-8 — so a request to pay large sums before a proper contract is a warning sign, not a normal step.
Has the developer actually become late?
This is where many buyers move too fast. A developer is not automatically late simply because the calendar has passed the delivery date. Before treating the developer as in default, the sequence has to be checked.
First, identify the completion deadline actually fixed in the contract. Then check article 618-7: the developer may benefit from an additional completion period of up to six months, but only if it informed the buyer one month before the original deadline expired. If that condition was met, the extra period may be lawful; if it was not, the developer cannot rely on it.
Only once the real deadline — original plus any valid extension — has passed can you properly say the developer is late. That conclusion is the trigger for the formal notice and the penalty analysis that follow, so it is worth getting right rather than assuming.
The 1% monthly delay penalty — and its conditions
Article 618-12 provides a delay penalty of 1% per month of the sum owed, capped at 10% per year. It is reciprocal: it can be owed by the developer for a construction delay, or by the buyer for a payment delay — whichever party is in default.
The important conditions are easy to miss. The penalty does not start the day after the contractual deadline: it runs only one month after the defaulting party receives a valid formal notice from the other. A clause that completely exempts the developer from liability for an unjustified delay is void. And these protections operate within a contract made in the legal form, which is another reason the preliminary contract's formality matters.
In practice this means the first concrete step, once you have confirmed the developer is genuinely late, is usually a properly served formal notice — the act that starts the clock — rather than an immediate demand for a penalty.
If the project has stopped or is not delivered
A stalled or abandoned project is the most serious scenario: works have stopped, the developer no longer responds, handover looks impossible, or there is a permit, title, financing or security problem behind the scenes.
The legal directions here can include a formal notice, checking and invoking the completion or refund guarantee, a claim to compel completion, a claim for judicial termination and restitution, and damages. If the developer is in financial distress, the buyer may become a creditor in an insolvency process — a separate field with its own rules. None of these routes guarantees full recovery, and the realistic outcome depends heavily on the guarantee in place and on what assets and security exist.
The completion or refund guarantee
One of the strongest protections in the current framework is article 618-9: after the preliminary contract, the developer must provide the buyer either a completion guarantee (ensuring the works are finished) or a refund guarantee (returning the instalments paid if the contract is not performed). The implementing decree 2.17.318 sets out how these guarantees are provided.
For a buyer in difficulty, the practical questions are concrete: does a guarantee actually exist, who issued it, what exactly does it cover, are its conditions met, has it expired or been released, and which of the two guarantees applies to your situation? A guarantee is not an on-demand cash machine — it responds under its own terms — but establishing whether it exists and what it covers is often the single most decisive step when a project is in trouble.
If you have paid more than half the price
Article 618-10 gives a buyer a specific protective tool. For a registered (immatriculé) property, once the advances paid exceed 50% of the sale price, the buyer may request a prénotation on the land title, on production of the preliminary contract and under the statutory conditions.
A prénotation is worth understanding for what it is and is not. It records the buyer's claim on the title and can help protect the buyer's position — but it is not ownership, and it is not a guarantee that the sale will complete. Where you have already paid a large share of the price, asking whether this protection has been put in place is a sensible question.
Terminating the contract and recovering money
If you want out with your money back, the law does not offer a simple self-cancellation. Termination is governed, subject to article 618-19, by article 618-14, which sets statutory compensation by reference to the construction stage reached: 15% of the amounts paid where the structural (gros-œuvre) works have been completed, and 20% of the amounts paid where the finishing works and the habitation or conformity certificate stage have been reached.
There is a specific protection where the developer is the one at fault on timing. Where the developer fails to respect the agreed handover deadline (subject to the article 618-7 extension), the buyer may terminate without owing compensation and may be entitled to compensation of 20% of the amounts paid. This is a real protection, but it is not an automatic windfall for every late delivery: it depends on the conditions being met and on the procedural route being followed.
So the honest answer to "can I cancel and get everything back?" is that termination and a refund may be available, through the guarantee and the courts, on conditions tied to the stage and the facts — not instantly and not guaranteed.
When is the property legally finished?
A property is not legally complete just because the works look finished. Under article 618-15 completion is tied to the habitation permit or conformity certificate, and under article 618-16 the final sale contract is linked to the architect's completion/conformity documentation, the habitation or conformity certificate, the distinct title(s) where applicable, and payment of the remaining price.
This is why paying instalments does not, by itself, make you the owner: ownership passes with the final deed and its registration, not with a bank transfer or a set of keys. Once the developer has obtained the completion documents it notifies the buyer, and the buyer then has a short statutory window (in the order of sixty days) to conclude the final sale; a refusal within that sequence can lead, under conditions, to termination or to an action to compel the sale. The precise steps and periods should be confirmed against the current text for your specific file.
When the property does not match what was promised
Keep two different problems apart. Non-conformity means the property does not match the contract, the plans or the agreed specifications — a different layout, a smaller surface, missing equipment or parking, changed materials, different common areas. A construction defect (malfaçon) is a physical fault in the building. The first is a contract and conformity question; the second may fall under construction-guarantee law.
On surface, there is no fixed Moroccan tolerance percentage to rely on — a significant difference between the contracted and delivered area can raise a non-conformity issue, with remedies (a price adjustment, works, or, if serious enough, other remedies) turning on the contract, the plans, the size of the difference and the actual prejudice. Similarly, not every change to the plans is unlawful: what matters is the contract, the specifications, whether you consented, the permits, the materiality of the change and the prejudice it causes.
Defects that appear after delivery are a distinct subject with their own timeframes and guarantees, and not every defect is covered by ten-year (décennale) liability. That analysis is set out separately in our guide on construction and contractor disputes; here it is a boundary rather than the whole subject.
If the buyer is the one who defaults
The framework cuts both ways, and a credible view of your case means being honest about your own position. If the buyer delays payment, withholds an instalment, refuses to sign the final deed, or cannot secure financing, the buyer can be the party in default.
The same article 618-12 penalty applies to a buyer's payment delay, and refusing to conclude the final sale within the statutory sequence can expose the buyer to termination and to the compensation framework. Before treating the developer as the wrongdoer, it is worth checking that your own payments and steps have kept pace with the contract.
Foreign and non-resident buyers
Foreign and non-resident buyers face the same VEFA law, with the added difficulty of distance: you paid instalments from abroad, you cannot easily inspect the works, and communication with the developer can fade just when handover matters most.
A good deal can be handled without being permanently in Morocco. Reviewing the reservation and preliminary contracts, checking the payment history against the legal stages, verifying the guarantee and the title, sending a formal notice and running much of the litigation can be done by Moroccan counsel, often under a legalized power of attorney with a certified Arabic translation, while a local technical inspection is arranged on site. Some steps — signing, handover and snagging, or certain formalities — may still require presence or a representative, so "everything remotely" is not a promise anyone should make.
If you funded the purchase in foreign currency, preserving the banking evidence of that funding matters for the later transfer of resale proceeds under Morocco's exchange-control regime — the same investment-trail logic covered in our guide on buying a hotel in Morocco.
Evidence to preserve now
- The reservation contract and the preliminary contract, and any final documents.
- All payment receipts and bank transfer records.
- The project plans and the agreed specifications.
- The brochure, renders and marketing material (useful, though not automatically contractual).
- The developer's emails and messages, and any formal notices exchanged.
- Dated photos and videos of the construction progress and of any non-conformity.
- Delivery notices and the habitation or conformity documentation, if issued.
- The guarantee documents and the title / land-registry information.
- Any technical report, and — for a foreign buyer — the power of attorney and proof of foreign-currency funding.
Matching your problem to the first step
- Developer late: check the contractual deadline and any valid article 618-7 extension before treating the developer as in default, then consider a formal notice.
- Asked to pay a lot, early: compare what is demanded against the article 618-6 stages and remember that payment before a proper contract has no legal effect.
- Project stopped: check the completion or refund guarantee, the title and the progress, and consider the termination route.
- You want a refund: identify your transaction stage, then look at article 618-14, the guarantee, and the procedure.
- The property changed: compare the plans and specifications and gather non-conformity evidence.
- You have paid more than half: check whether an article 618-10 prénotation can protect your position.
- You are a foreign buyer abroad: preserve payment evidence, arrange a power of attorney, and organise a local inspection.
What a lawyer can actually do
An off-plan dispute is won on where you sit in the legal sequence and on your evidence, and that is what a lawyer organises. In practice the work can include reviewing the reservation and preliminary contracts, verifying the legal stage you have reached, checking the payment history against the statutory stages, and reviewing the title and the guarantee.
From there it may involve a formal notice, negotiation with the developer, coordinating a technical expertise, and pursuing performance, the guarantee, delay compensation, termination and a refund, or damages — before the competent court, and for a foreign buyer, with representation coordinated from abroad.
What a responsible lawyer will not do is promise the ending. No one can honestly guarantee that money will be recovered, that the contract will be cancelled, or that the developer will finish. Those outcomes depend on the facts, the guarantee, the developer's solvency and the court; the value of counsel is in building the strongest version of your case and choosing the right route at the right stage.
Frequently Asked Questions
What can I do if my developer is late in Morocco?
First confirm the developer is actually late: check the contractual deadline and whether it validly took an additional period of up to six months under article 618-7 (which requires informing you one month before the deadline). Once the real deadline has passed, a formal notice is usually the first step, and a 1% monthly penalty can apply from one month after that notice.
When does the 1% monthly penalty apply?
Under article 618-12 the penalty is 1% per month of the sum owed, capped at 10% per year, and applies to whichever party is in default. It does not start the day after the deadline — it runs from one month after the defaulting party receives a valid formal notice.
Can the developer take an extra six months?
It can, but only under conditions. Article 618-7 allows an additional completion period of up to six months where the developer informed the buyer one month before the original deadline expired. If that condition was not met, the developer cannot rely on the extension.
Can I cancel and recover my money?
There is no simple self-cancellation. Termination and a refund may be available through the guarantee and the courts, with statutory compensation under article 618-14 of 15% or 20% of amounts paid depending on the stage. Where the developer missed the agreed handover deadline, you may terminate without owing compensation and may be entitled to 20% of amounts paid — on conditions.
What are the legal payment stages?
Article 618-6 caps payments by stage: up to 5% at reservation; up to 5% at the preliminary contract (or 10% with no reservation); up to 10% at the start of works; up to 60% across three construction stages; and up to 20% at the final contract and handover. Payment demanded before a proper contract has no legal effect (article 618-8).
What guarantee should the developer provide?
Under article 618-9 the developer must, after the preliminary contract, provide either a completion guarantee or a guarantee to refund your instalments if the contract is not performed. You should check whether it exists, who issued it and what it covers — it is not an automatic on-demand payout.
What if I have already paid more than half the price?
For a registered property, once your advances exceed 50% of the price you may request a prénotation on the land title under article 618-10. It helps protect your position, but it is not ownership and not a guarantee that the sale will complete.
What if the delivered apartment does not match the plan?
That is a non-conformity question, distinct from a construction defect. Remedies (price adjustment, works, or, if serious, others) depend on the contract, the plans, the size of the difference and the prejudice. There is no fixed Moroccan surface-tolerance percentage to rely on.
What if construction stops entirely?
Check the completion or refund guarantee first, along with the title and the progress. Options can include a formal notice, a claim to compel completion, judicial termination with restitution, and damages; if the developer is insolvent you may become a creditor. Recovery is never guaranteed.
Can a foreign buyer handle the dispute from abroad?
Much of it — contract review, checking payments and guarantees, formal notice and litigation — can be handled by Moroccan counsel under a power of attorney, with a local technical inspection arranged on site. Some steps, such as signing or handover, may still need presence or a representative.
Which court hears an off-plan dispute?
It depends on the parties. Where the buyer is a consumer, the case is generally heard by the Tribunal de Première Instance and consumer-protection rules may add safeguards; a professional or investor buyer may be before a different court. The competent court should be confirmed for your specific situation.
Related guides
Buying Property in Morocco as a Foreigner: Legal Checks and Risks
This guide provides general, informational guidance on the legal checks commonly recommended before buying property in Morocco as a foreigner, and the risks to be aware of during the process.
Construction Dispute in Agadir, Morocco: Defects, Contractor Delays and Legal Options
An informational guide for an owner facing a construction dispute in Agadir, Morocco — including foreign owners: defects and poor workmanship, non-conformity, incomplete works, delay, disputed extras, reception and reservations, preserving evidence, judicial expertise, ten-year liability and the role of a lawyer.
Property Dispute in Agadir: Classify the Conflict, Check the Property, Act
An informational guide for owners and non-resident or foreign owners: how to identify the type of property dispute in Agadir, why a property's registration status changes the analysis, and how to prepare before choosing an amicable or judicial route.
Note: this website provides general legal information and does not replace professional advice based on the facts and documents of each case.